Farmers have expressed concerns about a new high-voltage transmission line planned to be built across eastern Henderson County, and officials with the project said Wednesday night at an open house that they are going to work with farmers and landowners to find the best route—and pole placement—for them.
In some regard, those connected with the Reid to Indiana Kentucky power line, or RIKY, are receiving kudos from farmers for the way they are working with residents affected. But also, farmers are worried about the effects the power line will have on their operations.
“I’m not saying those people aren’t nice, but there are things that have come up they haven’t considered,” said J.C. Hicks, who lives in Niagara and farms throughout Henderson County.
RIKY officials on Wednesday night agreed, saying that’s why they are holding the open houses. At the second of two public meetings this week—this one at the community building at Sandy Lee Watkins Park off Ky. 351—officials said they were gathering information from landowners and farmers as an attempt to find the most agreeable way forward for farmers and landowners.
The 25-mile transmission line, carrying 345 kV, is planned to run from the Reid substation on the Big Rivers site in Webster County to a spot across the Ohio River in Warrick County, Ind. Jennifer Beatty, the director of communication for contractor LS Power, said Centerpoint will build a substation at that point in Indiana and then pull it from that to areas in the state. Electricity will also flow south, like a highway, and run to the Reid substation for disbursement from there, RIKY officials said.
They also said that the need for power in this area currently causes congestion in transmission and having another power line will allow for electricity to more easily get to where it needs to go. And that will allow for reliable electricity and stable rates, Beatty said.
Hicks, along with others, are worried that the placement of monopoles on which the transmission line will be carried will cause farming operations to suffer.
For example, he said that turning a 120-foot-wide sprayer around a pole would cause an operator to pull up to a point, back up, spin around and make other directional changes all the while the spray hits the same piece of ground, which would over-pollute the soil with chemicals.
“It can kill a crop,” Hicks said.
Beatty repeated a statement that Mike Bruno, the project manager, made in a previous Hendersonian article, saying the goal is to place the monopoles on property lines or near ditch beds—not in the middle of fields.
Another top concern are the easements that RIKY will have to obtain to place the monopoles on private property. Bruno said the easements will need to be 150 feet wide and there may be access needs as well.
Prices will be determined based on the fair market value of the land with a dollars per acre number derived from independent appraisals, he said. Bruno added that project officials intend to come up with a uniform offer based on the appraisals instead of going into negotiations on each piece of property.
Another concern brought up Wednesday night involved the property valuation of not just the acres needed to place a pole, but the farm as a whole. David Baird, a Niagara farmer, said he wondered what would occur to the valuation of the farm as a whole with poles placed on the land and a transmission line crossing over it.
Currently the project has a preferred route proposal, with a couple route segment alternatives. Finding a final route still needs to occur, which officials said will be helped by hearing the public comment at the open houses.
Next up the RIKY project team will begin working with landowners to obtain required easements in 2027 with an anticipated start of construction in 2028, according to a project timeline displayed at the Wednesday open house. It is expected for the transmission line to be in service in 2030.
Officials with the project say that it came about after the Midcontinent Independent System Operator, or MISO, completed an analysis of its system in 2022 and determined the transmission line was needed to improve durability and reliability of the system in this area. Local utilities are members of MISO.
Bruno said that MISO regularly conducts an analysis of its system to determine where improvements are necessary. In 2024, this project was one of many in MISO’s portfolio that needed to be addressed, Bruno said. Big Rivers also advocated for the improvements, he said.
After the request for proposals were submitted, Republic Transmission/LS Power won the bid in 2025.
After Wednesday evening’s meeting and a Tuesday open house at the Brain Injury Adventure Camp lodge, RIKY officials will still be accepting comments from the public. To do so, click here. Comments can also be made by calling 270-894-RIKY.