See key provisions, executive summary and staff summary below
The Henderson City-County Planning Commission recommended that Henderson County Fiscal Court approve an ordinance for wind energy conversion systems at a Wednesday special called meeting.
Now, the ordinance will be sent to the fiscal court for its consideration, which if recent history is indicative, will garner passage by the court.
The ordinance establishes standards for commercial wind facilities in unincorporated Henderson County.
Among the standards are:
- A total turbine height of 200 feet. This is more stringent than current state regulations that allows for a max height of 350 feet from the ground to the hub.
- A heavy industrial zoning (M-2). Commercial wind facilities are conditional uses onll in the M-2 zoning district, according to a summary of the WECS ordinance written by planning commission staff.
- One mile setback from non-participating occupied structures and residential zoning district boundaries.
- A noise limit of 35 decibels at non-participating occupied structures.
There are also environmental standards, decommissioning and financial assurance, and property owner protections among other standards.
The only discussion of a possible change to the ordinance Wednesday evening involved changing language about the property owner protections to match with a battery energy storage system ordinance proposal that is going through the process of being adopted.
In the proposed BESS ordinance language, a company is obligated to offer a property valuation, whereas in the WECS ordinance that the planning commission just recommended, a company only must have property valuation available, said Planning Commission Executive Director Brian Bishop.
Making that change did not occur at the meeting.
Another point discussed at a previous meeting was the process of notification if a company applies for a variance to the height requirement of a wind turbine. A previous draft said that notification must be sent out to residents within one mile of the wind turbine. The recommended version says that residents within five miles must be notified, Bishop said.
Below are standards of the WECS ordinance that the planning commission has recommended.